Control & Protection Panel & SCADA System for TTC .01 & 02 Solar farm – 50MW

FRA Completed TTC01 and TTC02 . solar power plants

TTC Solar Power Plant No. 01 was built on an area of ​​69.5 hectares. In which, the area to install the system of solar panels is 42.53 ha; with a scale of 68.8 MWp, with a total investment of more than 1,500 billion VND, officially started construction of site leveling and items on May 25, 2018.

According to the representative of the investor, the project was put into commercial operation on March 6, after nearly 10 months of construction.

The two solar power plants TTC 1 and TTC 2 in Tay Ninh were co-invested and operated by Thanh Cong Group and Gulf Energy Group (Thailand) and operated since mid-2019. At that time, the Thai group was owned by the Thai group. 49% capital but in the last change, Gulf has increased its holding to 90%. Mr. Prasert Thirati – Director of Gulf Vietnam Company is also the legal representative of TTC Green Energy Investment Joint Stock Company, Gulf Tay Ninh 1 Joint Stock Company, Gulf Tay Ninh 2. In addition to the projects Solar power project in Tay Ninh, Thai group also owns wind power projects in Ben Tre with the ownership rate of 95%.

FRA & TTC01, TTC02 – The 5th solar power plant out of 7 grid-connected solar power plants!

With this project, FRA is fortunate to cooperate with JGC/Japan corporation, one of the largest general contractors in the world in the field of electricity.

This project FRA provides the following equipment and services:

– Entire TBA second items: Protective control cabinet, AC/DC, Charging cabinet, battery, etc.

– Metering system, Electronic dispatching system.

– System of fault recording and power quality monitoring.

– Scada/Telecommunication system TBA 110kV brand Pacis/Schneider & FRA.

– RTU, PPC, DCS system for Solar Farm factory with Pacis/FRA brand.

– All energizing services and factory commercial operation certification.

Once again, thank you very much to the brothers FRA, JGC & TTC – TTC01 & TTC02 Team! After only 4 days at the construction site, the duo FRA – Hong Son & Minh Hieu together with the JGC brothers completed the ETE test of TTC02 factory with 3 centers A0, A2 & SPC, TTC02 already ready. ready to tie the net!

https://nangluongsachvietnam.vn/d6/vi-VN/news/Khanh-thanh-Nha-may-Dien-mat-troi-TTC-so-01-va-TTC-so-02-tai-Tay-Ninh- 6-165-3860