ENERGIZING THE PROJECT OF HANGING WIRES WITH 2 220KV LINES THANH HOA – NGHI SON – QUYNH LUU

The Northern Power Projects Management Board (NPMB) has completed the project of hanging the wire of 2 220kV lines Thanh Hoa – Nghi Son – Quynh Luu on the 220kV line Thanh Hoa – Vinh and energised at 1:03 on the 28th. /4.

Scale of project to pull ACSR 330/43 conductor with a length of 82km, including 67 anchorages from Ba Che 220kV substation to Nong Cong 220kV substation, Nghi Son 220kV substation, Quynh Luu 220kV substation; construction and installation of a new 220kV roadway at Ba Che 220kV substation, along with a number of other items.

NPMB has completed the wiring of 2 220kV lines Thanh Hoa – Nghi Son – Quynh Luu

The project, invested by the National Power Transmission Corporation, plays an important role in releasing capacity for Nghi Son 2 BOT Thermal Power Plant through the 220kV power grid, increasing the reliability of the power system, especially contributing to ensuring stable power supply for the load in Thanh Hoa, Nghe An and northern provinces before this year’s hot season.

The rope pulling work has been implemented since the beginning of January 2022. During the construction process, due to the characteristics of the line crossing with many 110kV lines supplying power to important industrial loads in Thanh Hoa and Nghe An provinces, the construction power cut-off encountered many difficulties. However, NPMB and the contractor made great efforts to overcome difficulties, completed energizing the entire project to celebrate the Liberation of the South, the unification of the country on April 30 and the International Labor Day on May 1.